Opportunities for Adaptive Reuse
By Mike Roselli, PE, PLA –
A vacant building or underused parking lot may offer more possibilities than you might think. If you’re an owner, tenant, or developer willing to consider a different idea, adaptive reuse of an existing property can reactivate a space for a new business or investment opportunity. Our new Celebree School of Cary project is an example of how to discover what a site can become, what’s already there to support it, and which changes make it work.
Case Study
Located on Crescent Green in Cary, and originally designed by Withers & Ravenel, is a commercial site developed in 1995. The original building has provided commercial office space for over thirty years.
This is the site of the future Celebree School of Cary, where we’re helping owners Hetal Shah and Sonali Patel convert existing office space into a childcare facility. The available tenant space gave them a place to start, but our task as the site design team was to make the surrounding site support a very different operation than the original site was intended for. I had a conversation with Shah who said they were targeting a Spring 2027 opening, subject to the final construction schedule.
The biggest question for the team was where to put the outdoor play areas required. There was plenty of space surrounding the building, but it was occupied by a large, underused parking field. We determined exactly how much parking the final building configuration would need, where it needed to be, and whether we could rearrange it to accommodate the school. That involved coordination with the existing building owner, Cary staff, the project architect, and a study of the impacts to existing drainage areas and utilities.
“You see a building and imagine what it could become, but there’s so much planning, coordination, and problem-solving that happens behind the scenes,” said Shah. “It takes a lot of people working together, and you learn something new at every step.”
This is exactly the kind of adaptive reuse challenge I enjoy: examining each part of the site and determining how to more efficiently provide the highest and best value for the owner and their tenant.
Testing the Use
When evaluating a property for redevelopment, we have to understand the operation early. How and when will people arrive? How long will they stay? What happens outside the building? Which requirements are essential to the business, and where is there flexibility?
For a childcare operator, a building with enough classroom space is only part of the answer. Outdoor play areas, parking, and safe movement between the building and the grounds all compete for space. On this project, the parking area was an opportunity to accommodate something the office use hadn’t needed: a playground.
But for another site and a different use, other constraints or requirements may make or break the deal. For a restaurant, the questions might involve deliveries, outdoor seating, and utility demand. A medical office will have a different pattern of arrivals and parking needs. Very quickly we find that the exact same property can produce very different answers depending on the use.
Understanding how the proposed operation fits the existing infrastructure is the beginning of our conceptual work, and the most useful early deliverable is a concept that tests those relationships. An owner should be able to understand what can stay, what needs to move, and what still needs an answer before committing to a purchase or lease.
Doing Your Due Diligence
Existing infrastructure can carry real value, but it can also create obligations and limitations that aren’t obvious during a property tour. A thorough review of runoff patterns, existing stormwater facility limitations, and utility capacities must be done during your due diligence period, and the sooner the better.
That’s because the scope of site work can drastically change the approvals required, the time needed to obtain them, and the overall costs associated with necessary site improvements.
Early coordination between the civil engineer, architect, and mechanical engineers helps identify these improvements sooner in the process because changes to the building can cascade into access and fire protection requirements, an experience Shah is now familiar with.
“The team worked through so many details with us, and the Town of Cary helped us understand the process and what was needed along the way. Having people like Mike who were willing to answer questions and help us work through the details made all the difference.”
Making the Numbers Work
The economic case for reuse depends on how much value the existing property actually contributes to the new operation.
A lower lease rate can make a location attractive, but the next question is how much of an investment is required of the operator. Site work, interior renovation, building systems, approvals, and the time before opening all belong in that comparison. For a leased property, the allocation of those costs between landlord and tenant matters, too.
A willingness to consider a different layout or an unconventional property can open up your options, but it also helps to distinguish the parts of an operation that are essential from those that can adapt to the location. That gives the design team room to solve problems while protecting business priorities.
If you’re evaluating a property for redevelopment or a change of use, let’s chat. Bring the intended use and the questions that are holding up a decision and we’ll be ready to start.
—
Celebree School of Cary is anticipating an opening in Spring 2027 and is excited to start connecting with families. Specific enrollment and opening information will be available soon.
Mike Roselli, PE, PLA serves as Vice President of Underfoot Engineering and serves the community on the Town of Cary Planning and Zoning Board and the Cary Chamber of Commerce Board of Directors. Want your next development to succeed by design? Let’s connect.